132kV Kesinga-Junagarh line was charged on 03.12.2019.
132/33kV, 20 MVA Transformer at Potangi Grid S/s charged on 15.09.2019.
1X40 MVA, 132/33kV Agarpara S/s charged on 30.08.2019.
1X160 MVA, 220/132/33kV Jayapatna S/s charged on 11.07.19.
132kV Bhadrak-Anandapur line charged on 03.07.2019.
1X20 MVA, 220/33kV Kashipur S/s charged on 30.06.2019
1X160 MVA, 220/132kV Aska S/s charged on 02.06.2019
3rd 315 MVA ICT charged at 400/220kV Mendhasal Sub-station on 28.02.19.
220/33kV, 2nd 20 MVA Transformer charged at Narsinghpur Grid S/s on 27.02.19.
1X40 MVA, 132/33kV Chikiti S/s charged on 25.02.19.
1X40 MVA, 132/33kV Chandbali GIS S/s commissioned on 20.02.2019.
2X20 MVA, 220/33kV Keonjhar GIS Sub-station commissioned on 31.12.2018.
Permission for initial Energisation of 132KV Nuapada RTSS Feeder Bay and associated 132KV SC line from 132/33KV Grid Sub-Station, Nuapada for power supply to Nuapada RTSS of East Coast Railway.
2nd 40 MVA Transformer at Tushra charged on 21.12.18
Lapanga 400kV Sub-station Bus charged on 03.11.18
Sterlite-Lapanga 400kV LILO Line on MCT Tower charged on 05.11.18
Ib-Lapanga-400kV Ckt-II charged on 03.11.2018
Ib-Lapanga-400kV Ckt-I charged on 03.11.2018
1X40 MVA, 132/33kV Udala S/s charged on 16.09.2018.
132kV Line from Nuapatna to Banki charged on 28.08.2018
1X40 MVA, 132/33kV Khuntuni GIS S/s charged on 31.05.2018
1X40 MVA, 132/33kV Ghense Sub-station commissioned on 13.04.2018.
1X100 MVA and 1X12.5 MVA, 220/132/33kV Bargarh New S/s was charged on 21.03.2018
2nd 40 MVA at 220/33kV Malkangiri S/s and 132/33kV Kantabanji S/s was commissioned on 16.03.2018.
1X40 MVA, 132/33kV Grid S/s at Kantabanji commissioned on 28.02.2018.
1X20 MVA, 132/33kV Dhenkikote S/S commissioned on 24.02.2018
1X12.5MVA 132/33kV Podagada Substation was energised on 09.02.2018 at 19.10 Hrs.
2nd 40 MVA Power Transformer at 132/33kV Bhograi S/s charged on 02.02.18.
1X40 MVA, 132/33kV Tirtole S/s commissioned on 05.01.2018
2nd 132/33kV, 20 MVA Transformer at Mania (Tangi) energised on 27.12.2017
132/33kV Muniguda Grid S/s was charged on 29.11.2017
2nd 20 MVA Tfr at 220/33kV Bonai S/s charged on 16.10.17
The 132kV LILO line from 132kV Jagatsinghpur-Paradeep to Tirtole S/s charged at 16.02 hrs on 08.09.2017.
The 132kV Salipur-Kendrapara line was charged on 29.07.17.
1X20 MVA, 132/33kV Tushra S/s charged on 26.07.2017
2nd 12.5 MVA Transformer at 132/33kV Olavar S/s charged on 24.07.2017.
2nd 20 MVA Power Transformer at 132/33kV Padampur S/s was charged on 21.07.2017
The 132kV Dhenkanal-Nuapatna 2nd Ckt was charged on 23.06.2017
1X20 MVA, 220/33kV Bonai Grid S/s was energised on 12.04.2017
2X160 MVA, 2X40 MVA, 220/132/33kV GIS Smart Automated Station at Chandaka B commissioned on 31.03.2017
3rd 40 MVA, 132/33kV Power Transformer at 132/33kV IIT Argul S/s was commissioned on 31.03.2017
1X12.5 MVA, 132/33kV Olavar S/s was commissioned on 30.03.2017
1X40 MVA, 132/33kV S/s at Bhograi with 132kV LILO of Kuchei-Jaleswar line commissioned on 29.03.2017
2X20 MVA, 132/33kV Khajuriakata S/s was commissioned on 28.03.2017
1X40 MVA, 220/33kV Malkangiri S/s was commissioned on 28.03.2017
2nd 40 MVA POwer Transformer at 132/33kV Sarasmal S/s was energised on 27.03.2017
220kV Balimela-Malkangiri line was energised on 24.03.2017
The 220kV Bidansi-Cuttack Line charged on 29.11.2016
One no. 160 MVA Auto Transformer and One no. 20 MVA Power Transformer was charged at 220/132/33kV Puri(Samangara) Grid S/s on 29.08.16.
The 2nd 160 and 20 MVA Transformers at 220/132/33kV Atri Grid S/s was charged on 17.08.2016 at 18.28 and 18.40 hrs respectively
Sample EventTest1
Transfer Order- 14003
1X12.5 MVA, 132/33kV Grid S/s at Mania(Tangi) charged on 31.03.201611
1X12.5 MVA, 132/33kV Grid S/s at Mania(Tangi) charged on 31.03.2016
Celebration of 11th Foundation Day & Cultural Festival
44.636kms of 132kV line from Patnagarh to Padampur charged on 24.02.2016
220/132/33kV Grid S/s at Atri charged on 24.02.2016
The new 20MVA, 132/33KV, BHEL make transformer has been charged at 15.42hrs on Dt.06.01.2016 in 132/33KV Grid S/S, Anandapur.
" The Vedanta IPP(Unit-2 and 4) syncronised with Meramundali system at 400kV at 13.16 hrs on 06.01.2016"
"209kms of 400kV Lapanga-Meramundali DC line charged on 30.12.2015"
1X12.5 MVA, 132/33kV Grid S/s at Somnathpur near Balasore charged at 14.12hrs on 11.12.2015
11TH POWER CUP FIXTURE
OPTCL Receives 9th ENERTIA Award 2015 for best performing Transmission utility
The 2nd 40 MVA Power Transformer at 132/33kV Grid S/s at Kalunga was charged at 12.20 hrs on 04.11.2015
" The 2nd 40 MVA Power Transformer at 132/33kV Grid S/s at Kalunga was charged at 12.20 hrs on 04.11.2015"
400kV Meramundali-Duburi line (Circuit-I) charged on 19.10.2015 at 20.20 hrs
"2X20 MVA, 132/33kV Grid S/s at Marshaghai charged on 16.10.2015"
"The 400kV Circuit-II of 400kV Meramundali-Duburi line charged on 11.09.2015"
The 132/33kV Grid S/s at Kalunga charged on 07.09.2015
" 132/33kV, 20 MVA, Lapanga Grid S/s charged on 11.08.2015 at 06.44PM"
The 132kV LILO of Nimapara-Puri line to Puri(Samangara) S/s charged on 15.07.2015
1X160 MVA, 220/132kV Grid S/s at Puri(Samangara) commissioned on 14.07.2015 at 14.14 hrs
220kV Pandiabil-Puri line charged on 10.07.2015 at 19.09 hrs
22.58kms of 220kV Atri-Pandiabil line charged on 25.06.2015
132/33kV Grid S/s at Konark charged on 29.06.2015
The 2nd 20 MVA Power Transformer at 132/33kV Nuapada Grid S/s charged on 23.05.2015
The 220kV LILO line to 220/33kV Infocity-II Grid S/s charged on 30.04.2015
The 132/33kV Grid S/s at Umerkote charged on 10.04.2015
The 132/33kV Grid S/s at Dabugaon charged on 10.04.2015
The 40 MVA Power Transformer at 132/33kV Grid S/s at IIT, Argul charged on 31.03.2015
The 132/33kV Grid S/s at Shamuka charged on 30.03.2015
Tender call Notice no. 4(1)
The 132/33kV Grid S/s at Jharsuguda (Sarasmal) was commissioned on 13.03.2015
The 132kV Under Ground Cabling project at Chandaka was commissioned on 08.03.2015
The 132/33kV Banki Grid Sub station commissioned on 29.01.2015 at 07.14 PM
132/33kV Grid S/s at Boud commissioned on 28.01.2015( 2:02 PM)
The 132kV Transmission line to 132/33/33kV Banki Grid S/s commissioned on 08.01.2015
11th Annual Sports Meet-201S
The 132/33kV Grid S/s at Nuapada commissioned on 27.12.2014
2nd 20 MVA Transformer at 132/33kV Kuchinda S/s charged on 24.11.2014
Awareness Programme on Effect of Dust & Smoke on Pulmonary System
PCB awareness , its disposal & elimination
132/33kV Grid S/s at IIT Argul commissioned on 06.05.2014
CMD's message on the occasion of 9th Foundation Day on 1st April, 2014.
NATIONAL WORKSHOP ON "SMART GRID"
132kV Bay with The 132kV line from Badagada S/s to Nimapada S/s with bay extension at Nimapada charged on 14.02.2014.
220kV line from Paradeep to IOCL charged on 12.02.2014.
132/33kV Grid Sub station at Barbil charged on 03.02.2014
2nd 12.5 MVA Power Transformer was energised on 25.01.2014 at 132/33kV Grid S/s Chandpur
BLOOD DONATION CAMP AT GRIDCO RECREATION CLUB BY GRIDCO FINANCE SERVICE WELFARE ASSOCIATION on 05/01/2014
The charging of 132kV line from M/s B.C.Mohanty Switching station to RTSS Tomaka on 09.12.2013
Free Multi Speciality Health At Pital Ganjam held By OPTCL On 13-11-2013
Jagatsinghpur-Pradeep DC line Charged on 01.11.13.
132/33 KV Grid S/S at Kuchinda Commissioned on 04.07.2013
220/33 KV Grid S/S at Laxmipur Commissioned on 06.10.2013
132 KV Line from M/S B.C Mohanty Switching Station to TOMKA RTSS Commissioned on 02.10.2013
M/S B.C Mohanty Switching Station Commissioned on 25.09.2013
132/33 KV Grid S/S at Chandpurr Commissioned on 14.08.2013
132/33 KV Grid S/S at Purushottampur Commissioned on 11.08.2013
Inauguration of Odisha Distribution System Strengthening project(ODSSP) by Honorable CM of Odisha Shri Naveen Patanaik at jaydev Bhawan
One Day Workshop on "Safety Practices for OPTCL System" has been conducted on 22nd September -2013 at Power Training Centre, OPTCL, Chandaka, Bhubaneswar by OPTRA in association with OPTCL. been conducted on 22nd,September -2013 at Power Training Center,OPTCL,Chndaka,Bhubaneswar by OPTRA in association with OPTCL.
Go-Live of eShakti HRCore and Pension Billing Modules for OPTCL Scheduled for 5th Sep 2013
Celebration of Foundation Day & Cultural Festival
Celebration of Foundation Day and Blood Donation Camp on 1st April,2013
OFFICE ORDER No.AWC-VIG-III-1/2010/5836 Dted.03.04.2013
Celebration of Foundation Day & Blood Donation Camp on 1st April,2013
"When safety is ensured, the confidence and efficiency level of employees get manifold."